TIMELINE
The Gascoyne Gateway project is in the first phase of development
As Australia’s first ‘green’ port, Gascoyne Gateway is committed to environmental management that regenerates and protects the area.
Project Phases
Currently, the Gascoyne Gateway project is in the first phase of development. In June of 2020, the Department of Jobs, Tourism, Science and Innovation was allocated lead agency status for the project from the State Government and the planning is in concept stage.
Community consultation is currently underway to understand community views and concerns and work together through the community reference groups to ensure the jetty meets the aspirations of the local community.
The planning and approvals phase of the project is predicted to take three years.

Timeline
December 2019
Gascoyne Gateway Limited created
June 2020
Lead Agency Status awarded
Mid-2020
Feasibility studies underway
October 2020